Multiple entry calculations in Storyline

Jun 26, 2016

Hi everyone,

I'm hoping to ask for some help in setting up a calculator with multiple parts for the e-learner to fill in.

I've attached an image of the slide I'm working on in Storyline2.

I'm hoping to set up the calculator to multiply whatever the elearner enters, and then for a check box or x mark to show up, depending on whether the answer is correct or wrong.

Eg.

(60 x 70)/(40x30)=3.5 Correct!

Thank you in advance!  

2 Replies
Walt Hamilton

Triggers: (all set to fire when user presses Calculate Now button and in this order)

Adjust Total = variable  [variable that contains (VTC) 60]

Adjust Total X variable VTC 70

Adjust Total / variable VTC 40

Adjust total / variable VTC 30

 Change state of  ShowResult to AnswerCorrect on condition Total = 3.5 (can be replaced with variable)

Change state of ShowResult to AnswerIncorrect on condition Total not = 3.5

These are the entries you make in the create trigger wizard.

 

 