I have a course where learners are give 3 quiz questions mid course. The questions are not tied to a results slide, it's a simple quiz to see if they need to be exposed to additional information.
...
TomKuhlmann
4 years agoStaff
I only created a single variable.
You only need one number variable that is adjusted on each correct layer. Add 1 when timeline of the correct layer starts,
Then you can advance if it = 3 or go to a remedial area if it is less than 3. There's no need to run a sum calculation.
The variable starts at 0. On the first correct layer +1, and so forth. If they get all three right, var should = 3. If they don't, it will be less than three.