Forum Discussion
SCORM files with results and score and expiry date
Hey Debashis,
I think I understand better now, thank you.
So you need a bit more information of how exactly these SCORM aspects and settings work?
No problem :)
TRACKING OPTIONS:
(When the learner has viewed / When the learner completes a quiz / Using triggers)
The key thing to remember here is that selecting more than one option here does not mean the user will be marked as complete only when BOTH options are true. No, its actually when the first one becomes true.
eg.
In your example above, you have selected both When the learner completes a quiz, and Using triggers.
So your user will be marked as Complete when either they complete the quiz (achieving a passing score) or if they arrive at a slide with the "Complete Course" trigger.
In other words, they are marked as completed right away when either of these things happen.
SCORE:
Whatever score the user gets (even if it doesnt pass) will be sent to the LMS as long as you are using SCORM 1.2, 2004 or xAPI.
The SCORE can also be used to mark a course as PASSED. To do this, you need to set the Passing Score setting. This is done within the Results slide OPTIONS inside Storyline.
NUMBER OF ATTEMPTS:
Again, this is set within the Results slide of Storyline.
NOTE - there is a specific setting for each question in Storyline so that you can set the number of Attempts. This is different than what you mean within the Results sent to an LMS.
The specific question Attempts setting, only means the user will have a certain number of retries on that specific question before it is permanently marked "Incorrect".
To set the number of attempts of a RESULTS slide, you need to set this up manually using variables and triggers. If done correctly this will now restrict the user so that they can only attempt a failed Results slide a certain number of times.
This Number of Attempts of a Results slide will only be sent and stored in an LMS if using SCORM 2004 (3rd/4th edition) or xAPI.
DATE OF PASS/FAIL:
Storyline will automatically pass out both the Session Time and Total Time values in SCORM 1.2, 2004 and xAPI.
The completion date is usually handled specifically by the LMS and isnt something Storyline has exposure to, and therefore not something we can directly set within a Storyline project.
Does that help at all? :)